Keeping up to date with the progress of the Aerodrome Upgrade Project.
Every effort is made to keep the project information on this site current. Contact Council for more information.

 

  Completed
  Not completed

 

 

 

April 2010

  • Options explored
  • Decision to proceed

 

May 2010

  • Civil Aviation Safety Authority (CASA) discussions
  • RPT Operator Review
   
     

June 2010

  • Landside Owner's Information
  • Airside Operator's Information
  • Stakeholders Information
  • Public Information
 

October 2010

  • Call tenders
   
     

December 2010

  • Negotiate tenders
 

January 2011

  • Award contract
   
   

February 2011

  • Commence construction
  • Project Management

June 2011

  • Project completion
  • Close out
   

 